ShareNelson County, Virginia After years and millions of dollars in infrastructure, International Broadband Electric Communications is apparently shutting down operations within the next month. Customer support apparently ceased for at least some Nelson County, VA customers on Friday December 30th, according to a letter below sent to a customer in Afton just before Christmas. We [...]
December 10, 2011
ShareColleen Nelson County, Virginia After nearly years in planning, construction officially started this past week for an ultra high speed fiber broadband network that will dramatically improve existing service for many Nelsonians, and bring service to many that don’t have it at all. The construction of the buried fiber line is starting in Colleen near [...]
November 11, 2011
ShareBOARD OF SUPERVISORS Thursday, November 10, 2011 Present: Mr. Joe Dan Johnson, Mr. Tommy Bruguiere, Mr. Allen Hale, Mr. Tommy Harvey and Ms. Connie Brennan VDOT REPORT: Mr. Don Austin reported that the crosswalk in front of the courthouse steps will be removed and painted next year. Ms. Brennan asked about putting a sidewalk along [...]
October 26, 2011
Share PLANNING COMMISSION Wednesday, October 26, 2011 Present: Ms. Philippa Proulx, Mr. Mike Harman, Ms. Linda Russell, Mr. Mike Tapager and Ms. Connie Brennan (Board Liaison and non-voting) SPECIAL USE PERMIT/WILLIE PARRISH: The applicant applied for a permit to place a second mobile home on property located at 1885 Cub Creek Road, Roseland. The property [...]
August 12, 2010
ShareLovingston Nelson County, Virginia Progress continues on Nelson getting a fiber optic backbone in place for the county to provide the next generation of ultra high speed internet to much of the county. Nelson’s Broadband Advisory Committee held its first meeting Wednesday afternoon in Lovingston. The purpose of the committee is to study and advise [...]
April 25, 2009
ShareThis is the latest update received from IBEC on Friday 4.24.09 Nelson County, Virginia Martins Store Substation BPL Update April 24, 2009 This has been a better week. We have had crews most of the week and have been able to work on issues, although they were rained out Monday and part of Tuesday. While [...]
April 17, 2009
Share Nelson County, Virginia Martins Store Substation BPL Update – April 17, 2009 There is little to report this week as the crews were all pulled to do storm work. They will return Monday and we will continue to optimize the networks. We have done a better job with the map. The new one shows [...]
April 11, 2009
ShareNelson County, Virginia Martins Store Substation BPL Update April 10, 2009 Several customers have requested a map of the various headends so that when we mention progress on the various headends you have a better understanding of where we are talking about. This is more difficult than you might imagine since the electric grid does [...]
April 4, 2009
ShareMartins Store Substation BPL Update April 3, 2009 This week we finished the Woodsmill 1 headend. This means that all the backbone units are installed for every circuit except what we call the Nellysford circuit which runs South down Rockfish Valley Highway. There is about 2 weeks worth of work left to finish all the [...]
March 20, 2009
ShareFrom: “IBEC Customer Service” Date: March 20, 2009 5:22:12 PM EDT To: “info” Subject: Martins Store Broadband over Powerline Update March 20, 2009 Martins Store Substation BPL Update March 20, 2009 We have made significant progress this week. All backbone units on the Afton 3 headend have been hung. We expect to finish Woodsmill 1 [...]