BOARD OF SUPERVISORS
Thursday, September 25, 2008


Present: Mr. Tommy Harvey, Mr. Allen Hale, Mr. Tommy Bruguiere,
Ms. Connie Brennan, Mr. Joe Dan Johnson


CLASS III COMMUNICATIONS TOWER/NTELOS - Rockfish Valley Highway - Kier/White
property - deferred until the October 23rd Supervisors’ meeting.


FABER/SCHUYLER SOLID WASTE COLLECTION SITE - Mr. Carter reported that work
continues to evaluate the Schuyler site. He noted that after consultation
with a local funeral business, the expense to relocate the cemetery (two
grave sites) would be at least $5,400. He also reported that PGS, Inc. has
been authorized to perform preliminary geotechnical evaluation (borings) of
the site. Work has not yet been completed.


Meeting adjourned.


Copyright 2000-2008 by Rural Nelson, Inc. All rights reserved. Reports may
be reprinted or excerpted with attribution.



Comments No Comments »

Oct. 18 - Nov 16. An exhibition of new oil paintings by noted painter and UVA professor Richard Crozier at the Spruce Creek Gallery in Nellysford. The gallery is open Wed. - Sun from 11 until 5. 1368 Rockfish Valley Hwy (Rte. 151)
434-361-1859.



Comments No Comments »

12-4 pm @ Humpback Rocks Mountain Farm, BRP, MILEPOST 5.8, (540)943-4716, Free.



Comments 2 Comments »

2-4 pm @ Humpback Rocks Mountain Farm, BRP, MILEPOST 5.8, (540)943-4716, Free.



Comments No Comments »

12-4pm @ Humpback Rocks Mountain Farm, Blue Ridge Parkway, MP 5.8, (540)943-4716, Free.



Comments No Comments »

2-4pm @ Humpback Rocks Mountain Farm, Blue Ridge Parkway, MP 5.8, (540)943-4716, Free.



Comments No Comments »

IBEC-1


We spoke this afternoon with Amanda Langley, Customer Service Manager at IBEC in Alabama. Amanda tells us that crews were pulled off for Hurricane Gustav, but will be returning to Nelson County on Wednesday September 10th to resume installation. “They’ll be back tomorrow and working continuously, unless another hurricane hits, like Ike or anything where they need them for hurricane relief,” Amanda tells NCL by phone in a Tuesday afternoon interview.


One concern that has been expressed by people already signed up for BPL is seeing all of the crews working in one specific part of Nelson on the north side of Martins Store. “When we began training, the north circuit was convenient for training. Now that we are past the training point, a crew will be on each circuit and they’ll be built simultaneously,” Amanda continues.


Another concern has been that once the network has been built and all BPL equipment is installed, will there actually be internet service? Verizon, must install specialty “T-1″ lines to connect with IBEC’s lines. Until that process is completed it’s like have all of the pipes installed in your home, but no water. “We scheduled our T-1 installation 90 days ahead of the actual deployment,” Amanda adds. According to those calculations the request would have been put into Verizon sometime in the early summer. As of this post, the lines have not been installed.


IBEC has asked that anyone who has received their modem to call the number enclosed in the box and register the modem with them in Alabama. The directions in the box don’t specifically say to call, but they do need customers to register their modems as they get them.


Otherwise, NCL is in the process of checking with Verizon to see what their hold up is and will let you know.


Earlier post from the morning of 9.9.08
Many of you have been e-mailing wanting to know about the status of BPL implementation in Nelson County. Today the following information was posted on the BPL site.


Hurricane Gustav Relief
September 8th, 2008
Due to problems from Hurricane Gustav, our contractor teams have had to temporarily withdraw from the area. They are scheduled to return later this week and resume their duties, but may have to be recalled again due to the impending storm, Ike. We apologize for any inconvenience this may cause and will have our crews back on task immediately in your area, following the storms.


We had information that crews left during Gustav, but could not confirm that. Apparently this was put on the BPl site recently.


It would be a good idea for anyone interested in checking the status to check their site here:
http://bpl.coop/deploymentnews.php?zip=22920&submit=View+Updates


We will keep you posted as we know more.


From earlier posts in August
The long awaited installation of equipment to bring faster internet to rural sections of Nelson County began Monday afternoon out of The Martins Store Substation at the intersection of Route 6 & 151. However, in spite of equipment being installed, crews are still waiting on specialty circuits to be hooked to their equipment by Verizon Wireline crews. Generally, designs such as the BPL system being deployed in Nelson call for large bandwidth telephone circuits such as a T-1 or larger to provide the needed capacity to service their BPL system once installed. Since the telephone circuits are a special installation, it can take several weeks for that phase to be completed.


IBEC-2
A subcontractor crew has been assisting in the installation of special equipment along the power lines to make the system work.


The installation will continue until everyone that pre-signed has been hooked up.


If anyone gets the service and it’s working, place a comment here to let everyone know where you are and when you were activated.


We’ll keep you posted!


NCL


Previous posts from earlier information:


As we have been telling you here the work to bring BPL internet service to rural customers continues in the Afton & Faber areas out of the Martins Store Substation. That will eventually service many locations along Routes 151, 6 and U.S. 29 along with other roads off of those main connectors.


Today, NCL received the e-mail update regarding the status of the service:


From: amanda.langley@ibec.net
Subject: IBEC BPL Service Update
Date: August 4, 2008 3:13:32 PM EDT
To: info@nelsoncountylife.com


Dear Customer,


Thank you for signing up for IBEC’s BPL Internet Service. We have received your setup fees and are preparing to ship your BPL modem. You should be receiving your modem within the next two weeks. Because you have signed up for service during our deployment phase, you will be among the first customers in your area to have service. Signing up during this period also waives your installation fee because our crews will install equipment outside your home or business as we deploy the service on the powerlines in your area. We plan to have service up at your location within six weeks of receiving your modem, but will try our best to make this wait as short as possible.


In order to minimize delays, please call IBEC Customer Service to register your modem as soon as you receive it.


IBEC’s toll free number is 1-888-IBEC-BPL (1-888-423-2275) Option 1.


We look forward to serving you.


Thank you,
IBEC Customer Service


IBEC is supposed to be contacting us with more details, but as of this e-mail has not been in touch with us. We will let you know, when we know.


Anyone that gets the service or sees activity, please drop us a message here or post a comment on this thread (by clicking on the topic heading / title at the top which opens the comment section up below) so we can let others know.


NCL



Comments 1 Comment »

FYI- We will be canceling our RRES Golf tournament on Friday, October 17,
2008.


An alternate date may be set later this Fall.


Friday, October 17, 2008 CANCELED
Winton Country Club
Registration Fee- $250 per team (4 players)
Includes: 18 holes of golf, lunch & prizes!
12:00 pm Registration/Lunch
1:30 pm Tee Time - Captain’s Choice
6:00 pm Prizes
Call for more information:
434.361.1791



Comments No Comments »

BOARD OF SUPERVISORS
Tuesday, September 9, 2008


Present: Mr. Allen Hale, Mr. Tommy Bruguiere, Ms. Connie Brennan and
Mr. Joe Dan Johnson


Absent: Mr. Tommy Harvey


BOARD OF EQUALIZATION - Mr. Johnny Ponton gave the BOE’s final report,
noting that that Board had heard 286 real estate reassessment appeals of
which 187 were affirmed, 99 were decreased and 3 were increased.  The BOE
reviewed the assessed values for over 3,000 properties or approximately 20%
of the parcels in the county.  The number of appeals represented a 540%
increase over the previous reassessment (2003).  Mr. Ponton reported the
BOE’s recommendations for future reassessments, including development of
additional tax relief programs for those facing economic hardship; public
clarification and information of the reassessment and appeals process; and a
review of policies and procedures related to the county’s Land Use Program.
Supervisors agreed to discuss the issue further at a Board Retreat.


JAUNT ANNUAL REPORT - Ms. Donna Shaunesey, Executive Director, reported that
public ridership increased by 2% with the Piney River route increasing by
11%.  She noted that 64% of the riders are adults, 36% are seniors and 45%
are people of all ages with disabilities.  Ms. Shaunesey reviewed several
programs under development and several future initiatives for Nelson.


VDOT REPORT - Mr. Kevin Wright reported that work has begun on the Chapel
Hollow/Pounding Branch (Rt. 709) Rural Rustic Project.  He also reported
that design work on the Rt. 151 turn lanes for Rt. 635 is tentatively
scheduled to begin in May, 2009 with construction scheduled for May, 2010.


AFFORDABLE HOUSING - Mr. George Krieger, Nelson County Community Development
Foundation (NCCDF), reported on the organization’s use of funding awarded to
the county for development of affordable housing.  Supervisors then voted
4-0 to institute two affordable housing initiatives:


- Waive tipping fees at the county transfer station for debris generated
from demolition of substandard housing as part of rehabilitation projects
(estimated cost to county $2,500).
- Defer for 24-months the connection fees (not installation charges) to
county-operated water and sewer systems on NCCDF-owned property (costs to
county offset by increased user base and increased taxable real estate).


BLUE RIDGE TUNNEL - Supervisors voted 4-0 to adopt a resolution authorizing
the County Administrator to proceed with the next phase of professional
services provided by Spectrum Design, P.C. including the final design.  Mr.
Carter noted that there are VDOT Enhancement funds to pay for this phase of
the project but that securing funding for the actual construction will be
the challenge.


REZONING/MS. LINDA CATALANO - Mr. Boger reported that the applicant has
applied to rezone approximately 10 acres (original request was to rezone 33
acres) from Industrial (M-2) to Agricultural (A-1) to allow a family member
to build a house.  Supervisors voted 4-0 to approve the rezoning.


COURTHOUSE PROJECT - Supervisors voted 4-0 to approve a resolution approving
the final design, authorizing advertisement and receipt of construction bids
and authorizing staff to proceed with the necessary steps to provide funding
for the project.


FABER/SCHUYLER SOLID WASTE COLLECTION SITE - Mr. Massie Saunders reported
that, at the county’s request, he had visited the current dumpster site on
Rt. 617 (Rockfish River Road) to evaluate the possibilities for its use as a
permanent collection site.  He noted two immediately apparent problems with
the site - the Hardwick Cemetery (approximately 20′ in diameter) in the
middle of the site and a 40-60′ elevation drop on the site.  He said that
his initial opinion is that is will be an expensive site to develop.  Mr.
Saunders presented several potential layouts for the collection site.  Mr.
Bruguiere asked whether digging at the site is going to hit rock.  Mr.
Saunders said that anytime you have slopes like those on the site, you are
probably going to have rock.  Mr. Johnson asked whether Mr. Saunders was
saying the site was not suitable.  Mr. Saunders said that the other sites
considered are better suited but that the site could be made to work.  Mr.
Hale agreed, saying that additional site testing is needed.  Mr. Saunders
said that the next step would be to get drilling equipment to the site.


Mr. Hale reported that he had looked at another potential site of 8.41 acres
near the intersection of Rt. 670 and Rt. 620 across from Rock Spring Church,
but noted that the asking price is $225,000.  He reported that he and Mr.
Harvey met with the Cove Valley members last week with their members taking
no action on the county’s request.  He said that he does not believe that
property will be made available, although he noted that Mr. Harvey does
believe it could be an option.  Mr. Johnson said that he would like to see
further investigation of the Schuyler property and that he has no problem
with moving on the parcel that the county put an offer on on Bunny Lane.
Mr. Hale said that he does have a problem with the Bunny Lane property with
the traffic coming off Rt. 6.  He said that he thinks the county should do
the additional testing on the Schuyler property.  Ms. Brennan said that she
has problems with the Schuyler site and that having a road going around a
cemetery concerns her.  Mr. Hale noted that Mr. Harvey has made it clear
that he is opposed to the Schuyler site.  Supervisors agreed by consensus to
direct staff to develop a potential site layout for the Schuyler site and do
the soil borings based on that layout.


COUNTY ADMINISTRATOR’S REPORT - Mr. Carter reported on the following:


- Hightop Tower Project - pending receipt of a decision from The Nature
Conservancy.
- Biosolids - DEQ has received applications for four sites, totaling 572.1
acres, with the Synagro as the applicator.  The applications were deemed
incomplete and returned by DEQ.  Staff is working to complete an agreement
with Professor David Orvos of Sweetbriar College for service as the county’s
biosolids monitor.
- 2008 General Reassessment - The completion of the appeal hearings by the
BOE resulted in a net change of total values of $2,665,300 or $14,659.15 in
taxes.


PROPOSED AMENDMENT TO CODE OF NELSON COUNTY/FIRE PREVENTION AND PROTECTION -
With no public comment, Supervisors voted 4-0 to amend the code to allow 16-
and 17-year olds to receive training and certification as firefighters.  Mr.
Eddie Embrey, Chair, Emergency Service Council reported that the amendment
would allow for the training and preparation of young people so that when
they turn 18, they are ready to go in firefighting.  He said that those
under 18 would not be allowed to go into burning buildings or work traffic
at an accident scene and that each department’s bylaws would govern all
other activities for Junior Firefighters.


REZONING/MR. JEFF COFFEY & MS. TERESA NAGY - Mr. Boger reported that the
applicants have requested a rezoning of approximately 3 acres located at
2910 Patrick Henry Highway from Industrial/Floodplain (M-2) to
Business/Floodplain (B-1) to allow the renovation of the American Cyanamid
office building for apartments and other B-1 uses.  With no public comment,
Supervisors voted 4-0 to approve the rezoning.


CLASS III COMMUNICATIONS TOWER/NTELOS/ROCKFISH VALLEY HIGHWAY - Mr. Boger
reported that the applicant has applied for a permit to construct a 130-foot
metal tower with three flush-mounted antennas at 5016 Rockfish Valley
Highway across from the Rockfish Presbyterian Church.  He noted that the
proposed site is 215 feet from Rockfish Valley Highway in a wooded area.
Mr. Boger reported that the application includes a requested waiver to the
landscaping requirement as the site is in a wooded area and a requested
exception to Section 20-7-2e which prohibits a metal tower within the
viewshed of a Scenic Byway.  In addition, he noted that the county’s
consultant (Atlantic Group) had confirmed the data and site selection for
the tower.


Ms. Valerie Long, representing the applicant, presented photos of the site
and the balloon tests, noting that the balloon was not visible from
adjoining properties or from across the road at the church or garden center.
She said that it is, however, visible for about 1/10 of a mile when
approaching the site on Rt. 151 from the south.  Ms. Long reported that
nTelos had searched for another suitable site, both before the Planning
Commission review and again at the Commission’s request.  She said that
available property that would achieve the coverage needed was not found.


During the Public Hearing, MS. LAURA BURROWS said that she is opposed to the
tower.  She said that driving Rt. 151 safely is difficult without people
distracted using their cell phones.  She said that no one has seen the
year-round view of the tower since the leaves were on the trees during the
balloon testing.  Ms. Burrows said that a 130-foot tower should not be
approved on a scenic byway.
MS. KELLY KAHLE, owner of the nursery across Rt. 151 from the proposed site,
said that she had altered her business plan to fit the rural character of
the county and if she has to comply with county ordinances, so should a big,
out-of-county business.  She said that her main concern were adverse health
effects.  Ms. Kahle said that Rt. 151 is a Scenic Byway and should be
protected as such.
MR. BILLY SMITH, adjoining property owner, said that he is opposed as it
would be spot zoning.
MR. LARRY WHITAKER, Afton, asked the county to maintain their low-profile
standards for towers and not start changing the rules now.
MS. JUDY BARNES, Afton, said that she owns a 122-acre farm in the area and
lives there full-time.  She said that she moved to Nelson for the “beauty
and unspoiledness” and will never be able to sell recoup her investment as
no one will want to buy land so close to a cell tower.
MR. CURTIS SHEETS, Wintergreen, noted that in 1999, Emergency Services
purchased equipment to allow the transmission of electrocardiographs to
hospitals from ambulances.  He said that the transmission requires two
minutes of uninterrupted cell signal and that as of 2008, those
transmissions still cannot be made until the ambulance is out of Nelson
County.


Ms. Brennan said that she would like to see shorter towers along Scenic
Byways, a balloon test done after the leaves are off the trees and receipt
of something from the Department of Historic Resources prior to
consideration.  She said that she understands the emergency medical issues
but is concerned about the health issues too.  She said that she wants the
county to review its tower ordinance as soon as possible.  Mr. Bruguiere
said that the proposed tower is not just for the driving public but would
also allow area residents to get rid of their landlines, go wireless and get
broadband.  He said that the proposed tower would allow up to four
co-locations, reducing the number of towers in that area.  Mr. Johnson said
that he would like to see maps from the various county providers so the
county would have some idea where providers could co-locate.  Mr. Hale said
that he is conflicted on this issue but that the issue before the Board is
whether to allow an exception for a metal tower within a Scenic Byway.


Mr. Johnson then made a motion to postpone a decision indefinitely.  Mr.
Boger informed the Board that a decision is required, by ordinance, within
90 days.  Mr. Johnson then amended his motion to postpone for 90 days (Ms.
Brennan seconding the motion).  Supervisors voted 2-2 (Mr. Bruguiere and Mr.
Johnson voting no) on the amended motion.  Mr. Johnson (Ms. Brennan
seconding) then made a motion to postpone a decision until their next
meeting on September 25th.  Supervisors voted 3-1 (Mr. Bruguiere voting no).


CLASS III COMMUNICATIONS TOWER/AT&T/BUCK CREEK LANE - Mr. Boger reported
that the applicant has applied for an amendment to an existing permit to
allow AT&T to co-locate at 94 feet on an existing 107-foot nTelos tower on
Thomas Nelson Highway on property owned by Ms. Barbara Turner Lowery.  With
no public comment, Supervisors voted 4-0 to approve the amendment to the
permit.


CLASS III COMMUNICATIONS TOWER/NTELOS/WPOA, INC. - Mr. Boger reported that
the applicants has requested a permit to construct a 130-foot tower on
Hearthstone Lane in Stoney Creek across from the water tank in an area
designed as open space on the Wintergreen Master Plan.  The tower will
include three flush-mounted panel antennas plus a 23-foot Omni antenna for
Wintergreen Emergency Services.  The permit request includes a request for
an exception from Section 20-7-2a requiring a “fall zone” of at least 125%
of the tower height (162.5 feet in this case).  Ms. Valerie Long,
representing nTelos noted that the exception is requested because the lot is
narrow and it would be impossible to meet the requirement.  In addition, Ms.
Long noted that the structural engineer had provided a letter noting that if
the tower were to collapse, it would collapse upon itself rather than
falling over.


During the Public Hearing, MS. LAURA BURROWS, said that she is opposed
noting that cell towers are dangerous to helicopters and said that the
emergency helicopters that serve Nelson might stop flyer here if this tower
is constructed.
MS. KELLY KAHLE said that nTelos is requested yet another exception and
asked where it would end.  She asked the county to review the overall cell
tower plan and coverage before approving this tower.
MR. LARRY WHITAKER said that this would be two nTelos towers close to each
other.  He said that he is concerned that the height standards are being
overlooked.
MS. JUDY BARNES said that she is opposed to this tower.
MR. CURTIS SHEETS, Deputy Director of Wintergreen Property Owners’
Association (WPOA) said that the #1 complaint from property owners and
visitors to the resort is the lack of cell coverage.  He said that the
coverage for Wintergreen has been mapped and that he has worked with the
vendors to provide comprehensive coverage without overlap.  Mr. Sheets said
that there has not been opposition from the Hearthstone Lane property owners
and the WPOA Board of Directors has voted unanimously twice to approve this
tower.  He said that the emergency services helicopters that service this
area use night vision as well as designated landing zones and that a 130′
tower is not high enough to interrupt that service.


Mr. Hale said that this application is very difference from the last nTelos
request as the residents of that area want the service.  He said that the
exception is requested because of a change in technology (allowing the tower
to collapse upon itself) and is an exception that has been granted on other
applications.  Supervisors voted 4-0 to approve the permit with the
exception to the “fall zone” requirement.


Meeting adjourned.


Copyright 2000-2008 by Rural Nelson, Inc. All rights reserved. Reports may
be reprinted or excerpted with attribution.



Comments 1 Comment »

Wintergreen clouds

Wintergreen clouds

Tuesday was pretty much a cloudy day with scattered light showers about the area, with no one station really receiving any great rainfall as you can see from the totals below:


Rainfall totals as of 11:59 PM EDT Tuesday night:


-TUESDAY High / Low at NCL Magazine : Rockfish Valley : 78°/68° - RAIN : 0.02″ - YTD: 21.59″
-TUESDAY High / Low at NCL-TWNF : Wintergreen Mountain : 68°/62° - RAIN 0.06″ - YTD: 29.73″
-TUESDAY High / Low at NCL-Hatcreek Farm : Roseland, VA : 73°/65°- RAIN : 0.02″ - YTD: 28.25″
-TUESDAY High / Low at NCL-Tiger Fuel : Lovingston, VA : 75°/68° - RAIN : 0.04″ - YTD: 26.14″
-TUESDAY High / Low at NCL-Delfosse Winery : Faber, VA : 76°/68° - RAIN : 0.02″ - YTD: 21.00″


Temperatures remained cool with all of the cloud cover, but not much rain for anyone. Look for much cooler temperatures to move into the area today, with low 70’s for valley highs and lower 60’s for the mountains. We’ll start off cloudy and foggy, with perhaps some areas seeing limited partly sunny skies by afternoon.


We head into a pretty unsettled weather pattern for the next several days. Variable cloudiness hangs in the area off and on through the weekend with temps warming into the upper 80’s again by Sunday. We won’t see any widespread rain during the period, but a frontal boundary in the area clouds and showers are possible right on through Monday of next week.



Hurricane Ike continues churning in the gulf heading for Texas. By the end of the 5 day period Ike may head north into the U.S. mainland and from there could go most anywhere.